Admin Overview

Unified Monitoring Hub - Asset Area A

Active Permits 142 ↑ 12% from last week
Pending Approvals 28 Action Required
Safety Observations 512 This Month
SIMOPS Conflicts 3 High Risk

Recent Permit Activity

Permit ID Work Type Applicant Location Status Last Update Actions
WMS-2023-0892 Hot Work - Welding Khalid Al-Hashemi Raffinery Section B Pending Approval 2 hrs ago
WMS-2023-0890 Confined Space Entry John Doe Tank 402 - External Active 5 hrs ago
WMS-2023-0888 Electrical Isolation Sami Raza Substation 12 Closed 1 day ago
WMS-2023-0885 Work at Height Mark Stevens Cooling Tower C Rejected 2 days ago

SIMOPS Awareness

Conflict Detected: Section B

Hot Work (WMS-0892) and Gas Venting (WMS-0901) scheduled in proximity.

Nearby Operations

3 Active permits within 500m of your current location.

Quick Actions